The White House Blog
July 2010

The White House is becoming occupied!

June 2010

Glazing to the raggedy 'ruin' edge and it's 'Eyrie' are installed.

May 2010

Interior works make great progress and the sedum starts to flower.

April 2010

The scaffolding is (almost) all down.

March 2010

The steel stair is installed in the 'ruin' building.

February 2010

Enclosing the link between the 'ruin' building and the 'new' build, with a frameless glass wall and south facing glazed sliding panels.

January 2010

The first windows go in and the west wing stone wall is complete.

December 2009

Working on the west wall in a cold winter.

November 2009

The masons start work on the west wall, despite the very wet weather.

October 2009

Completion of the slating and views from the interior spaces are forming. 

August 2009

The timber frame goes up and the roof goes on.

July 2009

Constructing the 'new' west wing as the ground floor steelwork and timber frame are erected. 

June 2009

Reinforcement and shuttering for the raft foundations commence. 

May 2009

Spey Building and Joinery arrive, archeological excavations are undertaken and consolidation to the interior stone work are completed. The building is ready for the new concrete slabs to be poured. 

April 2009

Bad weather instigates inside work for the stone masons.

March 2009

The opening is completed and ready for the new link.

February 2009

Copings to the existing walls.

January 2009

Making room for the new construction and reclaiming the stone.

December 2008

Stabilising the structure